water utilitiesLow priorityopen

Valero flow meter project closeout

Benicia

Summary

With Valero set to cease operations in 2026, the city formally wound down its flow meter replacement project, cutting the cost from $497,082 to $121,399.89 for the work already performed.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Apr 21, 2026.

Impact analysis

💰Financial impact

The project closed at $121,399.89 instead of the original $497,082 contract price.

✅Who benefits

Taxpayers benefit from avoiding further spending on infrastructure serving a facility that is shutting down.